D.C. Metro – Purple Line Segment 6 & 2 Drainage

  • Client: PLTC (Lane Construction, Flour Construction & Traylor Brothers)

  • Owner: MTA Maryland Transit Authority

  • Project Value: $12 million

    Scope of Work Included:

    • • Storm Drain Piping 26,760 LF
    • • Storm Drainage Structures 427 EA
    • • Storm Drainage Structures Large Cast in Place 4 EA
    • • Several Structures over 30’ Deep requiring Supportive Excavation
    • • 16” Pritec Coated DIP Water Line Relocate 1,600 LF
    • • 6” & 12” Pritec Coated DIP Water Line 600 LF
    • • Cathodic Protection on Water Line
    • • Sanitary Sewer Relocation various sizes
    • • Electrical Conduit and Vaults

About This Project

Metro was looking to expand its vast network of rail lines to reach even more locations within the D.C. area. The proposed Purple Line Expansion would add 21 new stops from Bethesda to New Carrollton along the northern-inner loop of the Capital Beltway.

MCC contracted and completed work along various locations including in the heart of the beautiful, historic University of Maryland campus. This work posed many obstacles and challenges including existing unknown underground utilities, pedestrian detours on campus, and restrictive work areas.

Given the high-profile nature of the work, MCC represented the MTA/Metro/Contractor joint venture well, receiving letters of appreciation from local authorities and citizens for our safety program, cleanliness of worksites, professionalism, and craftsmanship. MCC continues to complete work for this ongoing project with final completion dates and commissioning of Fall 2023.

Gallery

100
101
102
103
104
105
106
107
108
109
110
111
112
113
PlayPause
100
101
102
103
104
105
106
107
108
109
110
111
112
113
previous arrow
next arrow